Ramadan 2027: when to place your order

Ramadan 2027 begins on 8 February. Work backwards from that date and a container order needs to be confirmed by the end of October 2026 — the season is closer than the calendar suggests.

The dates for Ramadan 2027

Ramadan 1448 AH is expected to begin on the evening of 7 February 2027, with the first fast on 8 February, and Eid al-Fitr around 9–10 March 2027. The dates follow the Umm al-Qura calculation and are confirmed by local moon sighting, so a one-day shift is normal in some markets.

That is roughly ten days earlier than Ramadan 2026 (18 February – 19 March). The lunar year is about eleven days shorter than the solar year, which is why the season drifts earlier every year.

Working back from the shelf date

Three numbers decide the calendar: production takes about 40 days from deposit and design confirmation (the lead time we quote), sea freight from China to Europe typically adds 30–40 days, and most buyers want stock on the shelf two to three weeks before the first fast.

StepWorking date for 2027What has to be true
Categories, quantities, target pricenow – mid October 2026 the sample and artwork round needs one to two weeks
Order confirmed, deposit paid, artwork approvedby 30 October 2026 this starts the 40-day production clock
Goods leave Yiwuearly December 2026 after production and inspection
Arrive and clear customsearly – mid January 2027 assuming 30–40 days at sea
On shelfmid January 2027 three weeks of buffer before 8 February

If your market is closer to China the transit leg shortens and the whole calendar moves later; if it is further away, move it earlier. Substitute your own sailing time and the same arithmetic works.

If you are later than that

Later orders are still workable — the constraint simply moves from production to transport. Tell us the date you need the goods and we will tell you which quantities and which shipping modes are realistic. Moving a seasonal range by air or rail costs more per cubic metre than sea freight, so it is usually worth doing only for the lines that sell out first.

What we need to quote

  • Item numbers or a description of the ranges you want
  • Quantities — rough is fine, minimums are set per item and can be reached by combining categories in one order
  • Destination country and port
  • The date you need the goods in hand
  • Any packaging or private-label requirement, and the test standards your market asks for

Send that through the enquiry form, or start from the catalogues if you are still choosing ranges.

The dates above are calculated from our published lead time of about 40 days from deposit and design confirmation, plus typical sea transit. The dates we commit to are the ones on your quotation.

Working on this now?

Send the item numbers and the date you need the goods — we will come back with pricing, lead time and the tests that apply.